The BTW Agro compost plant in Belarus is also moving along
Despite the restrictions caused by the coronavirus pandemic, work is ongoing on our largest investment currently in which we are the general contractor – BTW Agro. Construction works have been completed at 80%, and now we are also starting to assemble equipment & machinery for Phase I Zone
- The construction of fermentation bunkers and spigot aerated floors are 90% ready
- We are preparing to install technological equipment and machines for the raw materials mixing line and the Hoving substrate top loading system
- Four technological tanks with a capacity of 1000m3 are also supplied by Agro-Projects
Zone Phase II / III
- The construction of the main building for Phase II / III is 90% ready
- The structures for pasteurization and spawning tunnels made of CMU are erected, the tunnels are ready to start applying a protective coating of epoxy
- In mid-May, the assembly of climate control systems supplied by Magik Chłodnictwo began